A CDU (Coolant Distribution Unit) is the core piece of equipment in a liquid-cooled data center: it sits between the facility chilled-water system and the server coolant loop, using a heat exchanger to keep the two sides separate — facility water never enters the rack, and the coolant inside the rack is circulated back by pumps after exchanging heat through the CDU. By form factor, CDUs come in in-row, in-rack, and facility-edge types; by heat-exchange method, they fall into liquid-to-liquid and liquid-to-air categories (Vertiv CoolChip CDU official page).
Its role in AI compute racks: full-rack solutions like the GB200/GB300 NVL72 are rack-level liquid-cooled designs (NVIDIA official page; Supermicro spec sheet lists 132kW per system with liquid-cooled dual hot-swappable pumps), relying entirely on the CDU to distribute and circulate coolant after cold plates absorb the heat. CDU capacities vary widely: the Vertiv CoolChip line spans five models from 70 to 2300kW — in-rack at 121kW, in-row at 600/1350/2300kW (Vertiv official page), with a single large in-row unit able to serve multiple AI racks simultaneously.
| Item | Value / Basis |
|---|---|
| Positioning | Interface device between the facility water loop and the server coolant loop (Vertiv) |
| Capacity range per unit | Five models, 70–2300kW (Vertiv CoolChip series) |
| Form Factor | In-row / in-rack / facility-edge · liquid-to-liquid / liquid-to-air (Vertiv) |
| GB200 NVL72 reference | Full-rack liquid cooling · Supermicro spec lists 132kW |
The B300 comes in both Air-cooled and Liquid-cooled variants with identical compute; the difference lies entirely in the facility. An Air-cooled NVL8 runs as soon as power is connected. The liquid-cooled configuration (NVL16 liquid-cooled system or NVL72 full rack) requires a matching CDU — this is facility engineering, not an accessory shipped with the server. When purchasing liquid-cooled racks, make sure the contract clearly specifies CDU ownership (delivered with the rack or facility-supplied) and whether capacity matches the rack-level power draw.
Buyer's perspective: when inspecting a liquid-cooled rack, always check the cold plates, coolant manifolds, quick disconnects, and leak detection; on the CDU side, verify redundant pumps, filtration, and flow monitoring are in place (Vertiv ships redundant pumps and 50-micron filtration as standard, with leak detection and flow alarms supported) — missing any of these is an operational risk.