H200 (full name NVIDIA H200, part of the "Hopper" series) is a data center GPU announced by NVIDIA in November 2023 and shipping from June 2024 , also the memory-upgraded version of the H100: compute parity with the H100, per-card memory doubled to 141GB HBM3e , with bandwidth raised to 4.8TB/s[1]。

It is positioned as the mainstream workhorse for "large-memory inference and fine-tuning": in the era of large models, memory capacity determines how big a model you can fit, and the H200 delivers nearly double the memory space within the H100's procurement and operating ecosystem — which is why it remains a volume staple in the global spot market and is known for "holding its value with big memory."

In mainland China, the H200 was approved for China in December 2025 and shipped in volume from July 2026; channel prices have swung sharply with supply cadence (see "Market Band" and "Timeline").

Use Cases FIT

AIXX Index (0–100): estimated by this Pedia via weighted public specifications — memory 40% + interconnect 30% + ecosystem 30%, with weights adjusted by use case. 90+ flagship tier · 75+ Excellent · 60+ usable · below 60 not recommended. The methodology is transparent and verifiable, and does not constitute a performance guarantee.

LLM Inference 88AIXX Index
141GB of large memory fits a 70B-class model in FP8 on a single card, handling long contexts and batch concurrency with ease.
Model Training / Fine-tuning 85AIXX Index
Hopper ecosystem fully mature; the go-to choice for tens-of-billions-scale full-parameter fine-tuning and LoRA batch pipelines.
Long-context / RAG 92AIXX Index
4.8TB/s bandwidth × 141GB: the sweet spot for ultra-long-context and retrieval-augmented workloads.
Cost-sensitive Inference 90AIXX Index
Rental and purchase prices well below the Blackwell generation; best per-token cost in the large-memory camp.
Video Generation 78AIXX Index
10–20B-class video models carried easily on one card; compute isn't top-tier, so batch pipelines stack multiple cards.

History HISTORY

November 2023 , NVIDIA announced the H200: a memory-upgraded H100 with HBM3e 141GB and 4.8TB/s, slated for mid-2024 delivery[1]。

June 2024 , units shipped worldwide one after another, quickly becoming the volume workhorse for large-model inference and fine-tuning.

In December 2025 , the H200 was approved for China, with channel module prices around RMB 1.4M per module (per media reports[2]), with initial batches in the thousands of units.

From July 2026 , shipments to China scaled up; H-series prices fell across the board, and the H200 became the most abundantly supplied flagship large-memory model in the mainland spot market.

Technical Specifications SPECIFICATIONS

ItemSpecification
GPU CoreNVIDIA Hopper H200(SXM5)
Board Memory141GB HBM3e
Memory Bandwidth4.8TB/s per card
ComputeParity with H100 (roughly petaflop-class in FP8, with sparsity)
GPU-to-GPU InterconnectNVLink 4th Generation · 900GB/s
Board Power (TBP/TGP)Up to 700W (configurable)
Mainstream System Form FactorsHGX H200 8-card baseboard (Air-cooled / Liquid-cooled)
Previous Generation / Competing ProductHGX H100 80GB / B300(288GB,Blackwell Ultra)

Specifications are subject to NVIDIA's official public documentation[1]; system configurations vary by OEM and production batch.

80GBH100 · HBM3141GBH200 · HBM3e288GBB300 · HBM3eMemory per Card · Generation Comparison (NVIDIA official specs)

Generational Comparison · Three Generations at a Glance GENERATIONS

ItemH100 80GBH200B300
Board Memory80GB HBM3141GB HBM3e288GB HBM3e
Memory Bandwidth3.35TB/s4.8TB/s~8TB/s
Compute GenerationHopperHopper (same compute)Blackwell Ultra(FP4)
GPU-to-GPU InterconnectNVLink 4 · 900GB/sNVLink 4 · 900GB/sNVLink 5 · 1.8TB/s
One-line buying adviceBudget ceiling · largest ecosystemLarge memory · volume mainstayFlagship new purchase · next generation

Specs subject to NVIDIA's official public documentation; see the B300 entry for its column comparison.

Family Members FAMILY

Complete systems built on the HGX H200 baseboard come from multiple OEMs; commonly seen in the mainland spot market:

Dell HGX H200 8Supermicro HGX H200 8Gigabyte HGX H200 8Integrated platforms such as AMAX

Cooling & Deployment COOLING

The H200 mainstream is air-cooled HGX 8-GPU form factor : 700W-class SXM5 heat-sink-tower solutions are mature and deployable in existing data centers — its biggest deployment advantage over the next-generation liquid-cooled flagship. Some OEMs offer liquid-cooled variants, mostly in high-density custom projects.

Air-cooled heat sink tower, actual photo
Air-cooled heat sink tower · Photo
Rear of system, actual photo
Rear of the system · Photo

Model Compatibility MODEL FIT

Model / ScenarioMemory requirement (FP8 estimate)H200 DeploymentAIXX Index
DeepSeek R1 full (671B)~690GB8-card 1.128TB fits a full-size single-node deployment with reasonable headroom93
R1-Distill 70B-class~70GBDeployable on a single 141GB card, ample headroom95
72B-class open-source models~72GBSingle-card deployment, generous long-context headroom95
Video generation models (10–20B class)Approx. 20–40GBEasy on one card; suited to batch pipelines80

Memory estimated as FP8 weights ≈ parameter count × 1 byte; the AIXX Index reflects this library's estimation methodology, updated with measurements.

HGX H200 8-GPU module, actual photo
HGX H200 eight-card module · Photo
HGX H200 heat sink tower, actual photo
Front of the heat sink tower · Photo
NVLink Switches, actual photo
NVLink Switches · Photo
Rear of system, actual photo
Rear of the system · Photo
HGX H200 render (manufacturer image)
HGX H200 render · vendor image (NVIDIA official site)
Close-up of the GPU Mate midplane inside the Aivres KR6288
Aivres KR6288 internals: close-up of the GPU Mate midplane · Photo
Angled shot of an HGX H200 8-GPU tray installed
Angled view of the HGX H200 eight-card tray installed · Photo
Front NVMe bays and fan wall of the Aivres KR6288
Aivres KR6288 front (NVMe bays + fan wall) · Photo

Actual photos are added continuously as inspection batches are stocked; AI-generated images are never passed off as real photos.

Video Overview VIDEO

Community real hardware · Source: YouTube COMMUNITY HANDS-ON

Playback may not be available in some regions

Software & Ecosystem ECOSYSTEM

ItemRequirements / Status
CUDA12.4 and above (full Hopper support)
Driver550 series and above
Training frameworksPyTorch / TensorFlow officially support Hopper
Inference enginesvLLM / SGLang / TensorRT-LLM are all adapted
NetworkingConnectX-7 400G or an equivalent interconnect solution
Operating systemMainstream Linux distributions (Ubuntu 22.04+ etc.)

The Hopper ecosystem is the most mature after three years of refinement; software stack versions evolve over time — defer to NVIDIA's official releases.

Purchasing & Inspection PROCUREMENT

Three inspection points when buying an H200:

1
Verify serial numbers independently
The H200 looks highly similar to the H100; silkscreen markings and official firmware reports must be checked — "passing off an H100 as an H200" is a scam that has appeared in the spot market.
2
Measured memory bandwidth
Compare the 141GB and measured bandwidth against spec — memory is the core value of this generation and also the prime target for refurb tampering.
3
Batch and China compliance status
China supply fluctuates with policy cadence; batch, customs routing, and compliance status affect warranty and resale value.

The full six-item stress-test criteria (values anchored to the H200) are in this entry "How to Stress-Test" section.

How to Stress Test BENCH TEST

Six-item stress-test criteria, all values anchored to the H200: unbox and identify → single-card Burn-in Test (700W air-cooled tower, ≤85℃ with zero ECC errors = Pass) → full-system Full Load → memory bandwidth (4.8TB/s rated, ≥85% = Pass) → Interconnect Bandwidth (nccl-tests ≥750GB/s) → inference throughput (≥80% of public baselines).

① Unboxing identification nvidia-smi
Watch: card count · per-card VRAM · whether driver/CUDA versions match what was promised
Missing cards8/8 cards · 141GB+ firmware report
Missing cards or reduced VRAM → reject outright8/8 cards present · 141GB/card+ official firmware report
Fail : missing cards, less VRAM than stated, or version mismatch; Pass : all 8 cards present, full VRAM, versions consistent; Excellent : official firmware report available for cross-reference.
Plain talk: count the cards first, then check VRAM — this step alone filters out half the tricks.
② Single-card Burn-in Test gpu-burn 3600 or dcgmi diag -r 3 · 30–60 minutes
Watch: temperature · power draw · ECC errors (700W at Full Load, air-cooled tower)
75℃80859095℃
Excellent ≤80°C, no throttlingPass ≤85°C, zero errorsFail ≥90°C, hard throttle
Fail : any error, Card Drop, or artifacts; Pass : sustains Full Load, zero ECC errors for 1 hour; Excellent : temperature ≤80°C with no throttling throughout.
Plain talk: a Burn-in Test makes the card sprint at full effort for an hour — weak silicon shows its true colors on the spot.
③ Full-system Full Load 8-card parallel Burn-in Test · ≥2 hours
Watch: ECC counters across all 8 cards · whether frequency curves stay aligned
0.5h1h2h
Any card lagging behind → rejectZero fatal ECCTemperature curves flat as a line
Fail : any card errors or falls behind; Pass : zero fatal ECC, no abnormal throttling; Excellent : all eight curves smooth and consistent.
Plain talk: examine all eight cards together — whoever falls behind is the problem. A single good card isn't good enough; the whole family has to keep up.
④ Measured Bandwidth of VRAM bandwidthTest(CUDA bundled sample)
Watch: measured bandwidth ÷ rated bandwidth (H200 HBM3e rated at 4.8TB/s)
70%808595%
Fail <70%Pass ≥85%Excellent ≥95%
Fail : below 70% of rating — strong evidence the memory was swapped or degraded; Pass :≥85%; Excellent :≥95%。
In plain terms: if the memory has been tampered with, the bandwidth gives it away immediately — this is the hurdle refurbished cards fear most.
⑤ Interconnect Bandwidth Measured Bandwidth nccl-tests all_reduce benchmark
Watch: eight-GPU fabric bandwidth (NVSwitch; per-GPU NVLink rated at 900GB/s)
0.650.750.810.9TB/s
Fail <650GB/sPass ≥750GB/sExcellent ≥810GB/s
Fail : Below 650GB/s — some GPUs have downgraded interconnect, or there's a cable/substrate issue; Pass :≥750GB/s; Excellent :≥810GB/s。
In plain terms: the speed at which eight cards work hand in hand — one poor connection and it shows instantly.
⑥ Inference Throughput Measured Bandwidth vLLM Run a real model under load
Watch: tokens/s throughput ÷ the model's public benchmark
50%80%100%Benchmark +10%
Fail: won't run / throughput cut in halfPass: ≥80% of benchmarkExcellent: within ±10% of benchmark
Fail : Service won't start or throughput is cut in half; Pass : Reaches 80% of the public benchmark; Excellent : Within ±10% of the benchmark.
In plain terms: passing everything above isn't the end — actually running a large model once is the report card buyers want.
⑦ Stability Wrap-up (Required for Large Orders) Full Load burn-in for 24–72 hours
Watch: hourly temperature/power/error logs
24h48h72h
Any card drop or reboot → rejectZero fatal ECCZero abnormal downclocking throughout
Fail : Card drops, reboots, fatal ECC errors; Pass : Triple zero (zero fatal ECC, zero abnormal downclocking, zero card-drop reboots); Excellent : Monitoring curves attached for every hour.
In plain terms: winning a sprint isn't winning — running three days straight without incident is true stability.

Methodology note: The Pass/Excellent thresholds were compiled by this database based on common engineering practice (bandwidth as a share of rated values, temperatures per standard datacenter limits), and will be calibrated gradually as Measured Bandwidth data from Inspection Reports accumulates; this table constitutes no acceptance commitment — specifics are subject to contract terms. The measured items in this database's Inspection Reports are recorded per this table — NOT_EXECUTED means the item was not run; "not tested" is itself important information.

Shipping & Delivery LOGISTICS

1
Customs & Compliance Documents
Customs routing and compliance status of China-approved batches affect warranty and resale value; shipping documents must be verified and kept.
2
Shipping Insurance
Insuring high-value equipment at full invoice value is standard industry practice; shipping insurance terms and claims procedures should be written into the contract.
3
Joint Inspection on Arrival
Check seals, exterior, and serial numbers one by one against the Inspection Report; photograph and document any discrepancy on the spot.

OEM & Variants VENDORS

Same HGX H200 baseboard, but each vendor's system differs in form factor, cooling, and service — start your selection with the differences:

System VendorRepresentative Form FactorDifferentiatorsBest For
SupermicroSYS-821GE-TNHR (8U Air-cooled)The volume workhorse; widest availability and channel coverageSpot Purchase · Best Value
DellPowerEdge series (HGX H200 8)Global tier-one service network and enterprise-grade supportMultinational Deployment · Service First
GigabyteHGX H200 8 systemFlexible configurations, strong APAC channel presenceAPAC Channel Purchase
AivresKR6288 (8U Air-cooled)Fully reviewed by professional media; high transparencyIf you want public reviews before deciding
AMAX and other integratorsIntegrated platforms (e.g., university cluster projects)Project-based integrated deliveryBulk projects · Tender scenarios

AIXX Index · Four-Dimension Deployment Comparison AIXX INDEX

System VendorEase of InstallationMaintenance ConveniencePerformance DensityExpected Lifespan
Supermicro90858482
Dell90928485
Gigabyte85808680
Aivres86808581
AMAX and other integrators82808482

The AIXX Index is our catalog's estimation methodology (0–100, based on public form factor, cooling solution, and service network differences), updated with hands-on verification, and does not constitute a purchase commitment. Refer to official vendor releases for specific models.

Glossary Cards GLOSSARY

HBM3e Memory

High-bandwidth memory stacked beside the GPU. The H200 offers 141GB HBM3e and 4.8TB/s per card — memory is the core value of this generation.

NVLink Interconnect

Fourth-generation NVLink: 900GB/s direct interconnect between cards, making eight GPUs act as one.

SXM5 Mezzanine Package

GPUs are soldered directly to the baseboard (not plug-in cards); the HGX H200 8-card baseboard is the SXM5 form factor; inspection requires checking the baseboard along with it.

FP8 Precision

An 8-bit floating-point format, the mainstream inference precision; estimate memory footprint as FP8 weights ≈ parameter count × 1 byte.

China-Compliant Batch

The H200 was approved for China in December 2025; batch, customs routing, and compliance status directly affect warranty and resale value — a must-check on inspection.

Limitations & Controversies LIMITS

  • Generational Squeeze : outgunned above by the B300 (288GB HBM3e + FP4), squeezed below by a falling H100 — the criticism that "the H200 is just an H100 with more memory" coexists with the defense that "buying an H200 is buying memory"; this library takes no side.
  • China Supply Policy Risk : approval, volume shipments, and subsequent quotas all fluctuate with policy cadence, sending channel prices soaring and crashing — the single biggest external risk variable for holding an H200.
  • Refurb and Rebranding Risk : H100 units rebranded as H200s have appeared in the spot market (per inspection-agency reports); serial number checks and memory measurements are mandatory procedures.
  • Generational Debate : compute parity with the H100 means that if your bottleneck is compute rather than memory, the H200's price-performance edge narrows considerably — confirm your bottleneck is memory before choosing.

Market Band MARKET DATA

H200 · Reference Price Band
DateBasisRegionReference Price BandNotes
2026-10-20Hall Real-TimeUS (USD)$2.09M – 2.26M4 quotes › (batch asking prices)
2026-10-20Hall Real-TimeMainland China¥5,850.179M – 7,007.409M3 quotes › (batch asking prices)
2025-12China channel referenceMainland ChinaApprox. ¥1.4M / modulePer media reports[2] · On sale in mainland ›
2025-09Procurement CaseMainland ChinaA batch at ¥2.639MXi'an Jiaotong University AMAX H200 platform (public tender award info)
2024-06Overseas Anchor PriceNorth AmericaFrom $172,643 / card boardPublic channel list price (barebones basis)
Scope note: the market band reflects publicly available channel information and listed price ranges recorded in this library, provided for market reference only and constituting no offer to transact; prices fluctuate with batch, condition, quantity, and channel terms—actual price subject to the seller's quote. Price data sources for this library: AIXX Exchange (Zero-commission Matching; does not participate in transactions). Market snapshots have been accumulated daily since 2026-10-20.
Time Reference price band (estimated)
Region

Methodology: All three regions use 8-GPU system pricing, directly comparable —Mainland China: estimated from approved-for-China shipments starting 2025-12 (scarcity premium was high early on, easing after volume ramp in 2026-07; anchored to same-day listings on 2026-10 at 5.85–7M per unit , 3 units); North America: channel system list prices traced back with a gradual climb since launch (anchored to listings on 2026-10 at $2.095–2.268M per unit , 4 units, converted to RMB on the same axis in the chart); Europe: anchored to listed system quotes ( €3.189M per unit , Dell HGX H200). Other regions will come online automatically as listings accumulate in this library. Price data sources for this library: AIXX Exchange (Zero-commission Matching; does not participate in transactions, does not possess or speculate on transaction prices — hence the data's neutrality). The estimated band is for trend reference only; actual price subject to the seller's quote.

Price milestone timeline MILESTONES

FAQ FAQ

What's the difference between H200 and H100?

Same compute, double the memory: 80GB→141GB HBM3e, bandwidth 3.35→4.8TB/s. In one sentence: the H200 offers nearly double the memory while keeping the H100 ecosystem.

Can the H200 run the full DeepSeek R1?

Yes. The full FP8 weights of R1 are roughly 690GB, and an 8-GPU H200 system with 1.128TB total memory can deploy it single-node with reasonable headroom (see "Model Compatibility").

H200 or B300—how to choose?

If your bottleneck is memory capacity and budget matters: H200. If you want FP4 compute and next-gen interconnect: B300. They're one generation apart, and the price gap is an order of magnitude—first confirm where your bottleneck lies (see the B300 entry for comparison).

Why do China-market prices fluctuate so much?

Supply shifts with the rhythm of export policy toward China: approval→volume ramp→quota adjustments, each round directly rewriting channel prices (see "History" and the milestone timeline). This library logs data daily and makes no qualitative judgments.

Is there a risk of refurbished units?

Yes. H100s rebranded as H200s have appeared on the spot market. Independent serial-number verification plus memory testing are essential steps (see "Purchasing & Inspection").

B300HBM3eNVLinkFP8HGX H100 80GBBlackwell architecture

Model comparison and selection COMPARE

References REFERENCES

  1. NVIDIA official site — H200 product page https://www.nvidia.com/en-us/data-center/h200/
  2. H200 China channel module price around 1.4M yuan per module (2025-12-24) 
  3. Market band data — AIXX Exchange (listings on this platform and channel-informed ranges, updated daily) /hall.html
Versions and errata | This entry is maintained by the AIXX Pedia editorial team, AI-assisted drafting with human fact-checking. Updated 2026-10-20 · Version v1.1 · All changes are logged and traceable. Spotted an error? Submit via Corrections Channel ; corrections are published after verification and recorded in version history.

This Library
Editorial PolicyAbout This Library (Disclosure of Interests)Corrections Channel
Editorial Constitution Summary
Every claim sourcedDrawbacks always stated · corrections publicly loggedNo paid entries acceptedZero traffic-funneling or sales elements within entriesMarket data attached only as data modules
AIXX Family
AIXX PediaAIXX ExchangeAIXX News
Market data source: AIXX Exchange · © 2026 AIXX Pedia · An AIXX Product